Roosa Connect: Transportation Alternatives Program


Roosa Avenue Connect Project

Pedestrians and cyclists cross Roosa AvenueThe Roosa Connect project is creating pedestrian and cycle facilities along and across Roosa Avenue, from 9th Street (south end) to El Paso Street (north end).

Current Status

The City of Durango is wrapping up design revisions to submit the plans to CDOT for final review. The project is anticipated to be advertised for construction in spring of 2024. 

For more information, please call (970) 375-4955 or email Multimodal.


  1. About the Project
  2. Public Meetings

About the Project

Total Project Cost: $1.9 million
Project Grant Funding: Transportation Alternatives Program Grant $948,644
Local Match Total (Half Cent Sales and Use Tax Fund): $951,356
Status: 95% design (PDF) is complete! Construction for this project is anticipated in 2023.

The Roosa Connect project is a proposed 6-foot sidewalk and northbound bike lane along Roosa Avenue, on the east side of the roadway, from 9th Street (south end) to El Paso Street (north end).

The City received a $948,644 Transportation Alternatives Program grant to complete the project, which will complete 0.82 miles (4,322 feet) of ADA-compliant sidewalks and curb ramps, bringing the sidewalks up to current standards.

Design reached 95% completion by October 12, 2018. This 2016 Design and Engineering Project is being funded by 2015 Half Cent Sales and Use Tax funds.

View 95% Design Plans (PDF)
View 75% Design Plans (PDF)
View 30% Design Plans (PDF)

Roosa Connect project vicinity map